Ford Wind Park - Dagenham

2 turbines · operational · London

Wind farm facts

StatusOperational
County / regionLondon
Turbines2
Installed capacity5.9 MW
Turbine capacity2.96 MW
Tip heightnot recorded
Operator (or applicant)Ecotricity
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2004 2006 2008 2010 2012 2014 2016 2018 Project timeline Application submitted March 2003 Permission granted July 2003 Operational June 2004 Permission expired July 2017

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3158.

What the register tells us

The application was determined in about 4 months. A planning permission on this site expired in July 2017. The scheme has been operating for about 22 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 2.95 MW per turbine on average.