9 turbines · operational · Humberside
| Status | Operational |
|---|---|
| County / region | Humberside |
| Turbines | 9 |
| Installed capacity | 29.7 MW |
| Turbine capacity | 3.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Octopus Investments |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4647.
The application was determined in about 11 months. Construction to first power took about 14 months. The register records a refusal in May 2012 before the scheme progressed. Permission was ultimately granted on appeal in January 2013. A planning permission on this site expired in January 2012. The scheme has been operating for about 10 years. That works out at 3.3 MW per turbine on average.
See all wind farms in Humberside.