11 turbines · operational · Strathclyde
| Status | Operational |
|---|---|
| County / region | Strathclyde |
| Turbines | 11 |
| Installed capacity | 22.5 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | The Renewables Infrastructure Group (TRIG) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3886.
The application was determined in about 18 months. Construction to first power took about 12 months. The register records a refusal in September 2013 before the scheme progressed. Permission was ultimately granted on appeal in April 2014. A planning permission on this site expired in April 2020. The scheme has been operating for about 9 years. That works out at 2.05 MW per turbine on average.
See all wind farms in Strathclyde.