Freasdail Wind Farm

11 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines11
Installed capacity22.5 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)The Renewables Infrastructure Group (TRIG)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 Project timeline Application submitted October 2012 Refused September 2013 Permission granted April 2014 Granted on appeal April 2014 Under construction February 2016 Operational February 2017 Permission expired April 2020

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3886.

What the register tells us

The application was determined in about 18 months. Construction to first power took about 12 months. The register records a refusal in September 2013 before the scheme progressed. Permission was ultimately granted on appeal in April 2014. A planning permission on this site expired in April 2020. The scheme has been operating for about 9 years. That works out at 2.05 MW per turbine on average.