22 turbines · operational · Strathclyde
| Status | Operational |
|---|---|
| County / region | Strathclyde |
| Turbines | 22 |
| Installed capacity | 66 MW |
| Turbine capacity | 3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Ventient (formerly Infinis) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 7 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4368.
The application was determined in about 29 months. Construction to first power took about 20 months. A planning permission on this site expired in August 2017. The scheme has been operating for about 9 years. That works out at 3 MW per turbine on average.
See all wind farms in Strathclyde.