Galawhistle

22 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines22
Installed capacity66 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Ventient (formerly Infinis)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted March 2010 Permission granted August 2012 Under construction June 2015 Operational February 2017 Permission expired August 2017

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4368.

What the register tells us

The application was determined in about 29 months. Construction to first power took about 20 months. A planning permission on this site expired in August 2017. The scheme has been operating for about 9 years. That works out at 3 MW per turbine on average.