Galsworthy Wind Park

4 turbines · operational · Devon

Wind farm facts

StatusOperational
County / regionDevon
Turbines4
Installed capacity9.2 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Ecotricity
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted April 2008 Permission granted September 2008 Under construction May 2011 Permission expired September 2014 Operational November 2014

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4624.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 42 months. A planning permission on this site expired in September 2014. The scheme has been operating for about 12 years. That works out at 2.3 MW per turbine on average.

Nearby

See all wind farms in Devon.