8 turbines · under construction · Grampian
| Status | Under Construction |
|---|---|
| County / region | Grampian |
| Turbines | 8 |
| Installed capacity | 46.2 MW |
| Turbine capacity | not recorded |
| Tip height | 200 m |
| Operator (or applicant) | Energiekontor UK Limited / Uniper |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 8468.
The application was determined in about 10 months. Permission was ultimately granted on appeal in September 2022. A planning permission on this site expired in September 2027. That works out at 5.78 MW per turbine on average.