Garlenick Estate 2 - Wind Turbines

2 turbines · operational · Cornwall

Wind farm facts

StatusOperational
County / regionCornwall
Turbines2
Installed capacity4 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Airvolution Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 Project timeline Permission expired January 2011 Application submitted November 2012 Permission granted January 2013 Under construction April 2014 Operational June 2015

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3917.

What the register tells us

The application was determined in about 2 months. Construction to first power took about 14 months. A planning permission on this site expired in January 2011. The scheme has been operating for about 11 years. That works out at 2 MW per turbine on average.