17 turbines · operational · Powys
| Status | Operational |
|---|---|
| County / region | Powys |
| Turbines | 17 |
| Installed capacity | 34 MW |
| Turbine capacity | 2 MW |
| Tip height | 137 m |
| Operator (or applicant) | Renewables Infrastructure Group (TRIG) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 9 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3711.
The application was determined in about 84 months. Construction to first power took about 13 months. The register records a refusal in September 2013 before the scheme progressed. Permission was ultimately granted on appeal in May 2015. The scheme has been operating for about 9 years. That works out at 2 MW per turbine on average.