Gayton Le Marsh Wind Farm

8 turbines · operational · Lincolnshire

Wind farm facts

StatusOperational
County / regionLincolnshire
Turbines8
Installed capacity16.4 MW
Turbine capacity2.05 MW
Tip heightnot recorded
Operator (or applicant)Energiekontor UK
Turbine manufacturerSenvion
Turbine modelMM92

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted August 2011 Refused May 2012 Permission granted April 2013 Granted on appeal April 2013 Under construction February 2015 Permission expired April 2015 Operational February 2016

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4369.

What the register tells us

The application was determined in about 20 months. Construction to first power took about 12 months. The register records a refusal in May 2012 before the scheme progressed. Permission was ultimately granted on appeal in April 2013. A planning permission on this site expired in April 2015. The scheme has been operating for about 10 years. That works out at 2.05 MW per turbine on average.