Gedney Marsh

6 turbines · operational · Lincolnshire

Wind farm facts

StatusOperational
County / regionLincolnshire
Turbines6
Installed capacity12 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Wind Prospect
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted January 2003 Permission granted September 2003 Under construction May 2006 Operational July 2008 Permission expired September 2014

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3133.

What the register tells us

The application was determined in about 8 months. Construction to first power took about 26 months. A planning permission on this site expired in September 2014. The scheme has been operating for about 18 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Lincolnshire.