8 turbines · operational · Cambridgeshire
| Status | Operational |
|---|---|
| County / region | Cambridgeshire |
| Turbines | 8 |
| Installed capacity | 16 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Fenland Windfarms Ltd |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 3 years.
The register links a second scheme on this site (REPD ref 3765, Operational): 6 turbines · 2 MW each · applicant EDF/China General Nuclear Power Corporation. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3132.
The application was determined in about 6 months. The scheme has been operating for about 21 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 2 MW per turbine on average.
See all wind farms in Cambridgeshire.