GlaxoSmithKline Wind Project

3 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines3
Installed capacity7.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Glaxosmithkline
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted January 2010 Permission granted May 2012 Operational June 2013 Permission expired May 2016

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3841.

What the register tells us

The application was determined in about 28 months. A planning permission on this site expired in May 2016. The scheme has been operating for about 13 years. That works out at 2.5 MW per turbine on average.