Glen Kyllachy Wind Farm

20 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines20
Installed capacity48.5 MW
Turbine capacity2.5 MW
Tip height110 m
Operator (or applicant)Greencoat UK Wind
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Project timeline Application submitted June 2013 Refused September 2014 Permission granted April 2015 Granted on appeal April 2015 Permission expired April 2018 Operational January 2022

From application to operation, this scheme took about 9 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4371.

What the register tells us

The application was determined in about 22 months. The register records a refusal in September 2014 before the scheme progressed. Permission was ultimately granted on appeal in April 2015. A planning permission on this site expired in April 2018. The scheme has been operating for about 4 years. That works out at 2.42 MW per turbine on average.