20 turbines · operational · Highland
| Status | Operational |
|---|---|
| County / region | Highland |
| Turbines | 20 |
| Installed capacity | 48.5 MW |
| Turbine capacity | 2.5 MW |
| Tip height | 110 m |
| Operator (or applicant) | Greencoat UK Wind |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 9 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4371.
The application was determined in about 22 months. The register records a refusal in September 2014 before the scheme progressed. Permission was ultimately granted on appeal in April 2015. A planning permission on this site expired in April 2018. The scheme has been operating for about 4 years. That works out at 2.42 MW per turbine on average.