Glenbuck

1 turbines · operational · Co. Antrim

Wind farm facts

StatusOperational
County / regionCo. Antrim
Turbines1
Installed capacity2.3 MW
Turbine capacity2.3 MW
Tip height109 m
Operator (or applicant)Energia Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Scheme REPD 3961 Application submitted June 2005 Permission granted April 2007 Permission expired April 2012 Under construction April 2016 Operational March 2017 Scheme REPD 3962 Application submitted November 2006 Permission granted June 2011 Under construction April 2016 Permission expired June 2016 Operational March 2017

From application to operation, this scheme took about 12 years.

The register links a second scheme on this site (REPD ref 3962, Operational): 3 turbines · 2.3 MW each · 109 m tip height · applicant Energia Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3961.

What the register tells us

The application was determined in about 22 months. Construction to first power took about 11 months. A planning permission on this site expired in April 2012. The scheme has been operating for about 9 years. That works out at 2.3 MW per turbine on average.