Glenchamber Wind Farm

11 turbines · operational · Dumfries and Galloway

Wind farm facts

StatusOperational
County / regionDumfries and Galloway
Turbines11
Installed capacity27.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted October 2010 Refused September 2011 Permission granted July 2012 Granted on appeal July 2012 Under construction February 2015 Operational June 2016

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4638.

What the register tells us

The application was determined in about 21 months. Construction to first power took about 16 months. The register records a refusal in September 2011 before the scheme progressed. Permission was ultimately granted on appeal in July 2012. The scheme has been operating for about 10 years. That works out at 2.5 MW per turbine on average.