11 turbines · operational · Borders
| Status | Operational |
|---|---|
| County / region | Borders |
| Turbines | 11 |
| Installed capacity | 22 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Novera Energy |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
The register links a second scheme on this site (REPD ref 4578, Planning Permission Expired): 6 turbines · 2.5 MW each · applicant Muirhall Energy (formerly Infinis). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3538.
The application was determined in about 9 months. Construction to first power took about 10 months. A planning permission on this site expired in September 2010. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.
See all wind farms in Borders.