Glens of Foudland

20 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines20
Installed capacity26 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)Green Investment Bank (Blackrock)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2000 2001 2002 2003 2004 2005 2006 Project timeline Application submitted January 2001 Permission granted October 2001 Operational July 2005

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3311.

What the register tells us

The application was determined in about 9 months. The scheme has been operating for about 21 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 1.3 MW per turbine on average.