Goathill Quarry Turbine

1 turbines · operational · Fife

Wind farm facts

StatusOperational
County / regionFife
Turbines1
Installed capacity2 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Collier Quarrying Group
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted November 2011 Permission granted June 2013 Under construction May 2014 Operational December 2015

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4088.

What the register tells us

The application was determined in about 19 months. Construction to first power took about 19 months. The scheme has been operating for about 11 years. That works out at 2 MW per turbine on average.