Golticlay Wind Farm

11 turbines · under construction · Highland

Wind farm facts

StatusUnder Construction
County / regionHighland
Turbines11
Installed capacity72.6 MW
Turbine capacity6.6 MW
Tip height180 m
Operator (or applicant)RWE Renewables UK Limited
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Project timeline Application submitted October 2016 Permission granted March 2021 Granted on appeal March 2021 Under construction July 2025 Permission expired March 2026

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 5195.

What the register tells us

The application was determined in about 53 months. Permission was ultimately granted on appeal in March 2021. A planning permission on this site expired in March 2026. That works out at 6.6 MW per turbine on average.