11 turbines · under construction · Highland
| Status | Under Construction |
|---|---|
| County / region | Highland |
| Turbines | 11 |
| Installed capacity | 72.6 MW |
| Turbine capacity | 6.6 MW |
| Tip height | 180 m |
| Operator (or applicant) | RWE Renewables UK Limited |
| Turbine manufacturer | Nordex |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 5195.
The application was determined in about 53 months. Permission was ultimately granted on appeal in March 2021. A planning permission on this site expired in March 2026. That works out at 6.6 MW per turbine on average.