Goonabarn Farm Wind Turbines

2 turbines · operational · Cornwall

Wind farm facts

StatusOperational
County / regionCornwall
Turbines2
Installed capacity1 MW
Turbine capacity0.5 MW
Tip heightnot recorded
Operator (or applicant)George Richards Farms Partnership
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 2017 Project timeline Application submitted February 2013 Permission granted July 2013 Under construction January 2016 Operational April 2016

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3918.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 3 months. The scheme has been operating for about 10 years. That works out at 0.5 MW per turbine on average.

Nearby

See all wind farms in Cornwall.