🌬️ Onshore wind farm

Gordonbush (extension)
Highland

Recorded in WhichWindTurbine: 35 wind turbines in operation. Point the app at one of them to see its profile in real time.

35
turbines
70 MW
MW total
2 MW
per turbine

📍 11 turbines mapped — each dot is a turbine recorded in the database. Average position: 58.09723 N · 3.95281 W.

Gordonbush (extension)

35 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines35
Installed capacity70 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Scottish and Southern Energy (SSE)
Turbine manufacturerSiemens Gamesa
Turbine modelmodel not established
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

✓ Verified reference — turbine make and model

Siemens Gamesa · model not established · 11 turbines · 4.3 MW each

Source: SSE, first power press release, 2021-04, read on 2026-09-14. Corroborated by 3 further sources. Where OpenStreetMap tags differ, this record prevails.

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~2043201620182020202220242026today1234
  1. 1Jun 2015 — Application submitted
  2. 2Sep 2017 — Permission granted
  3. 3May 2020 — Under construction
  4. 4Jan 2021 — Operational

The register also records a planning permission expiry in Sep 2024, after construction had started: an administrative date with no effect on the wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 9 years.

The register links a second scheme on this site (REPD ref 3435, Operational): 11 turbines · 4.3 MW each · 150 m tip height · applicant Scottish and Southern Energy (SSE). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3662.

What the register tells us

The application was determined in about 58 months. Construction to first power took about 23 months. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Highland.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.