Gordonstown Hill Wind Farm

5 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines5
Installed capacity12.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Ventient (formerly Infinis)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted December 2008 Permission granted July 2009 Under construction July 2012 Operational March 2013

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3666.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 8 months. The scheme has been operating for about 13 years. That works out at 2.5 MW per turbine on average.