Gortfinbar

6 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines6
Installed capacity15 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Energia Renewables
Turbine manufacturerSiemens Gamesa
Turbine modelSWT 3.0-101

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted April 2006 Permission granted May 2009 Permission expired May 2013 Under construction September 2015 Operational December 2016

From application to operation, this scheme took about 10 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3933.

What the register tells us

The application was determined in about 37 months. Construction to first power took about 15 months. A planning permission on this site expired in May 2013. The scheme has been operating for about 10 years. That works out at 2.5 MW per turbine on average.