Grange

6 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines6
Installed capacity12.3 MW
Turbine capacity2.05 MW
Tip heightnot recorded
Operator (or applicant)Octopus Investements/Blue Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted November 2010 Refused April 2011 Permission granted January 2014 Granted on appeal January 2014 Under construction January 2015 Operational December 2015

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4069.

What the register tells us

The application was determined in about 38 months. Construction to first power took about 11 months. The register records a refusal in April 2011 before the scheme progressed. Permission was ultimately granted on appeal in January 2014. The scheme has been operating for about 11 years. That works out at 2.05 MW per turbine on average.