18 turbines · operational · Tayside
| Status | Operational |
|---|---|
| County / region | Tayside |
| Turbines | 18 |
| Installed capacity | 27 MW |
| Turbine capacity | 1.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | CRE Energy/ Scottish Power |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
The register links a second scheme on this site (REPD ref 3488, Revised): 18 turbines · 1.75 MW each · applicant CRE Energy/ Scottish Power. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3487.
The application was determined in about 46 months. Construction to first power took about 3 months. The register records a refusal in June 2006 before the scheme progressed. Permission was ultimately granted on appeal in June 2008. The scheme has been operating for about 18 years. That works out at 1.5 MW per turbine on average.