Green Park

1 turbines · operational · Berkshire

Wind farm facts

StatusOperational
County / regionBerkshire
Turbines1
Installed capacity2 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Ecotricity / Prudential
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted March 2004 Permission granted July 2004 Operational October 2005 Permission expired July 2017

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3210.

What the register tells us

The application was determined in about 4 months. A planning permission on this site expired in July 2017. The scheme has been operating for about 21 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 2 MW per turbine on average.