Greendykeside

2 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines2
Installed capacity4 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)A7 Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted September 2004 Permission granted May 2005 Operational November 2007 Permission expired May 2013

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3236.

What the register tells us

The application was determined in about 8 months. A planning permission on this site expired in May 2013. The scheme has been operating for about 19 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Strathclyde.