Greenvale AP Wind Turbine

1 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip heightnot recorded
Operator (or applicant)Greenvale AP
Turbine manufacturernot recorded
Turbine modelAcciona AW77-1500

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Scheme REPD 4374 Permission expired September 2010 Application submitted July 2012 Permission granted September 2012 Under construction May 2014 Operational August 2014 Scheme REPD 2821 Application submitted July 2011 Permission granted December 2011 Permission expired December 2018

From application to operation, this scheme took about 2 years.

The register links a second scheme on this site (REPD ref 2821, Revised): 1 turbines · 2 MW each · applicant Greenvale AP. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4374.

What the register tells us

The application was determined in about 2 months. Construction to first power took about 3 months. A planning permission on this site expired in September 2010. The scheme has been operating for about 12 years. That works out at 1.5 MW per turbine on average.

Nearby

See all wind farms in Cambridgeshire.