Haddo

2 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines2
Installed capacity4.6 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Private Developer
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted September 2006 Permission granted June 2009 Under construction May 2010 Operational May 2011 Permission expired June 2015

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3404.

What the register tells us

The application was determined in about 33 months. Construction to first power took about 12 months. A planning permission on this site expired in June 2015. The scheme has been operating for about 15 years. That works out at 2.3 MW per turbine on average.