Halifax Farm

1 turbines · operational · Leicestershire

Wind farm facts

StatusOperational
County / regionLeicestershire
Turbines1
Installed capacity1.6 MW
Turbine capacity1.6 MW
Tip heightnot recorded
Operator (or applicant)Wentworth and Harper
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 Project timeline Application submitted June 2014 Permission granted September 2014 Under construction May 2015 Operational September 2015

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4493.

What the register tells us

The application was determined in about 3 months. Construction to first power took about 4 months. The scheme has been operating for about 11 years. That works out at 1.6 MW per turbine on average.