Hall Farm Routh

12 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines12
Installed capacity24.6 MW
Turbine capacity2.05 MW
Tip heightnot recorded
Operator (or applicant)John Laing Environmental Assets Group/REG Power Management
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted October 2006 Refused January 2007 Permission granted February 2009 Granted on appeal February 2009 Permission expired February 2012 Under construction June 2012 Operational May 2013

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3948.

What the register tells us

The application was determined in about 28 months. Construction to first power took about 11 months. The register records a refusal in January 2007 before the scheme progressed. Permission was ultimately granted on appeal in February 2009. A planning permission on this site expired in February 2012. The scheme has been operating for about 13 years. That works out at 2.05 MW per turbine on average.

Nearby

See all wind farms in Humberside.