6 turbines · revised · Cumbria

Wind farm facts

StatusRevised
County / regionCumbria
Turbines6
Installed capacity12 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)REG Wind Power
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Original scheme Application submitted March 2011 Refused August 2011 Later scheme Application submitted November 2013 Permission granted October 2014 Under construction January 2017 Permission expired October 2017 Operational February 2018

The register links a second scheme on this site (REPD ref 4316, Operational): 6 turbines · 2.2 MW each · applicant REG Windpower/ BlackRock. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3737.

What the register tells us

The register records a refusal in August 2011 before the scheme progressed. That works out at 2 MW per turbine on average.