Halsary Wind Farm

15 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines15
Installed capacity34 MW
Turbine capacity2.3 MW
Tip height120 m
Operator (or applicant)Scottish Power Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Project timeline Application submitted November 2009 Permission granted September 2013 Under construction February 2020 Operational March 2021

From application to operation, this scheme took about 12 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4636.

What the register tells us

The application was determined in about 46 months. Construction to first power took about 13 months. The scheme has been operating for about 5 years. That works out at 2.27 MW per turbine on average.