Hampole Wind Farm

4 turbines · operational · South Yorkshire

Wind farm facts

StatusOperational
County / regionSouth Yorkshire
Turbines4
Installed capacity8 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Good Energy (previously nPower Renewables)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted September 2008 Permission granted December 2009 Permission expired December 2010 Under construction June 2013 Operational March 2014

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3957.

What the register tells us

The application was determined in about 15 months. Construction to first power took about 9 months. A planning permission on this site expired in December 2010. The scheme has been operating for about 12 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in South Yorkshire.