20 turbines · operational · Strathclyde
| Status | Operational |
|---|---|
| County / region | Strathclyde |
| Turbines | 20 |
| Installed capacity | 13.2 MW |
| Turbine capacity | 0.66 MW |
| Tip height | not recorded |
| Operator (or applicant) | Scottish Power Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2711.
The application was determined in about 32 months. The register records a refusal in May 2019 before the scheme progressed. The scheme has been operating for about 26 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.66 MW per turbine on average.
See all wind farms in Strathclyde.