Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines20
Installed capacity13.2 MW
Turbine capacity0.66 MW
Tip heightnot recorded
Operator (or applicant)Scottish Power Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1995 1998 2001 2004 2007 2010 2013 2016 2019 Project timeline Application submitted February 1996 Permission granted October 1998 Operational November 2000 Refused May 2019

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2711.

What the register tells us

The application was determined in about 32 months. The register records a refusal in May 2019 before the scheme progressed. The scheme has been operating for about 26 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.66 MW per turbine on average.