Haswell Moor

5 turbines · operational · County Durham

Wind farm facts

StatusOperational
County / regionCounty Durham
Turbines5
Installed capacity10 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)E.ON UK Renewables Developments Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 Project timeline Application submitted November 2006 Permission granted December 2007 Under construction October 2010 Operational December 2010

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3507.

What the register tells us

The application was determined in about 13 months. Construction to first power took about 2 months. The scheme has been operating for about 16 years. That works out at 2 MW per turbine on average.

Nearby