Haverigg Repowering (Haverigg II)

5 turbines · operational · Cumbria

Wind farm facts

StatusOperational
County / regionCumbria
Turbines5
Installed capacity1.2 MW
Turbine capacity0.22 MW
Tip heightnot recorded
Operator (or applicant)Windprospect
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2003 2005 2007 2009 2011 2013 2015 2017 2019 Project timeline Application submitted April 2002 Permission granted August 2002 Operational May 2004 Permission expired August 2019

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3614.

What the register tells us

The application was determined in about 4 months. A planning permission on this site expired in August 2019. The scheme has been operating for about 22 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.24 MW per turbine on average.