Hawton Wind Farm

3 turbines · operational · Nottinghamshire

Wind farm facts

StatusOperational
County / regionNottinghamshire
Turbines3
Installed capacity9 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Temporis Capital
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted December 2011 Refused August 2012 Permission granted September 2014 Granted on appeal September 2014 Under construction September 2016 Operational March 2017 Permission expired September 2017

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4532.

What the register tells us

The application was determined in about 33 months. Construction to first power took about 6 months. The register records a refusal in August 2012 before the scheme progressed. Permission was ultimately granted on appeal in September 2014. A planning permission on this site expired in September 2017. The scheme has been operating for about 9 years. That works out at 3 MW per turbine on average.