Hazlehead

3 turbines · operational · South Yorkshire

Wind farm facts

StatusOperational
County / regionSouth Yorkshire
Turbines3
Installed capacity6 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Banks Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted September 2006 Permission granted March 2007 Under construction August 2010 Operational December 2011 Permission expired March 2015

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3937.

What the register tells us

The application was determined in about 6 months. Construction to first power took about 16 months. A planning permission on this site expired in March 2015. The scheme has been operating for about 15 years. That works out at 2 MW per turbine on average.