3 turbines · operational · South Yorkshire
| Status | Operational |
|---|---|
| County / region | South Yorkshire |
| Turbines | 3 |
| Installed capacity | 6 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Banks Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3937.
The application was determined in about 6 months. Construction to first power took about 16 months. A planning permission on this site expired in March 2015. The scheme has been operating for about 15 years. That works out at 2 MW per turbine on average.
See all wind farms in South Yorkshire.