High Haswell Wind Farm

2 turbines · operational · County Durham

Wind farm facts

StatusOperational
County / regionCounty Durham
Turbines2
Installed capacity4 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Hallam Land Management
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 Project timeline Application submitted April 2007 Permission granted December 2007 Under construction January 2011 Operational March 2011

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3050.

What the register tells us

The application was determined in about 8 months. Construction to first power took about 2 months. The scheme has been operating for about 15 years. That works out at 2 MW per turbine on average.