High Pow Farm

3 turbines · operational · Cumbria

Wind farm facts

StatusOperational
County / regionCumbria
Turbines3
Installed capacity3.9 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)REG Windpower (previously Cornwall Light and Power)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 Scheme REPD 4029 Permission expired October 2000 Application submitted July 2004 Permission granted October 2004 Operational March 2007 Scheme REPD 3087 Application submitted September 2003

From application to operation, this scheme took about 3 years.

The register links a second scheme on this site (REPD ref 3087, Revised): 3 turbines · 1.3 MW each · applicant Private Developer. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4029.

What the register tells us

The application was determined in about 3 months. A planning permission on this site expired in October 2000. The scheme has been operating for about 19 years. That works out at 1.3 MW per turbine on average.

Nearby