High Sharpley Wind Farm

2 turbines · operational · County Durham

Wind farm facts

StatusOperational
County / regionCounty Durham
Turbines2
Installed capacity2.6 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)REG Windpower (previously Cornwall Light & Power)
Turbine manufacturerQuiet Revolution
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 2007 Project timeline Application submitted April 2002 Permission granted June 2002 Operational December 2006

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3092.

What the register tells us

The application was determined in about 2 months. The scheme has been operating for about 20 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 1.3 MW per turbine on average.