Hill of Fiddes

3 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines3
Installed capacity6.9 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Infinis, previously Broadview Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 Project timeline Application submitted September 2007 Permission granted April 2008 Under construction July 2009 Operational February 2010

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3968.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 7 months. The scheme has been operating for about 16 years. That works out at 2.3 MW per turbine on average.