12 turbines · operational · Highland
| Status | Operational |
|---|---|
| County / region | Highland |
| Turbines | 12 |
| Installed capacity | 29.9 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Greencoat UK Wind |
| Turbine manufacturer | Enercon |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 10 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4121.
The application was determined in about 58 months. Construction to first power took about 25 months. The register records a refusal in May 2006 before the scheme progressed. Permission was ultimately granted on appeal in April 2010. The scheme has been operating for about 11 years. That works out at 2.49 MW per turbine on average.
See all wind farms in Highland.