Hill of Stroupster Windfarm

12 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines12
Installed capacity29.9 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Greencoat UK Wind
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted June 2005 Refused May 2006 Permission granted April 2010 Granted on appeal April 2010 Under construction November 2013 Operational December 2015

From application to operation, this scheme took about 10 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4121.

What the register tells us

The application was determined in about 58 months. Construction to first power took about 25 months. The register records a refusal in May 2006 before the scheme progressed. Permission was ultimately granted on appeal in April 2010. The scheme has been operating for about 11 years. That works out at 2.49 MW per turbine on average.