3 turbines · operational · Grampian
| Status | Operational |
|---|---|
| County / region | Grampian |
| Turbines | 3 |
| Installed capacity | 9.6 MW |
| Turbine capacity | 3.2 MW |
| Tip height | not recorded |
| Operator (or applicant) | LocoGen/ Green Cat Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3911.
The application was determined in about 25 months. Construction to first power took about 17 months. The scheme has been operating for about 10 years. That works out at 3.2 MW per turbine on average.